Project Phase Cost Estimate
Phase 1 – Spring 2024 – Eave Up $ 502,011
Escalation – 6.00% $ 30,121
Phase 1 Subtotal $ 532,132
Escalation – 14.00% $ 60,300
Phase 2 Subtotal $ 491,016
Phase 3 – Spring 2026 – Interiors/Systems $ 349,032
Escalation – 22.00% $ 76,787
Phase 3 Subtotal $ 425,819
Phase 4 – Spring 2027 – MAAB/ADA – Elevator $ 1,109,866
Escalation – 30.00% $ 332,960
Phase 4 – Elevator Subtotal $ 1,442,826
Phase 4 – Spring 2027 – MAAB/ADA – Conference $ 533,740
Escalation – 30.00% $ 160,122
Phase 4 – Conference Subtotal $ 693,862
Total – Phases 1 through 3 $ 1,448,967
Total – Phases 1 through 3 plus Elevator $ 2,891,793
Total – Phases 1 through 3 plus Conference $ 2,142,829.