Notice on MSBA Project Information
The MSBA updates the project information on the MSBA website on a regular basis; however, due to timing issues or other circumstances, there may be instances where the most up-to-date information does not yet appear. If you have questions or concerns about any of the project information, please contact the MSBA.
The Estimated MSBA Payment Amount Remaining is the maximum amount of funding that the District may still receive from the MSBA for the Project. The actual amount paid by the MSBA may equal an amount less than this estimated amount, as determined by an audit conducted by the MSBA.


List of Projects for the District are as follows:

School nameMSBAIDProject TypeProject PhaseTotal Project BudgetReimbursement RateEstimated Building Completion DateMSBA Amt Paid(to Date)Estimated MSBA Payment Amt RemainingAnticipated MSBA Investment Amt
Narragansett Middle201107200305GGreen RepairFinal Audit Approved$1,144,51159.84 %$663,544 $663,544
Phillipston Memorial201107200003GGreen RepairFinal Audit Approved$161,23259.84 %$78,095 $81,401
Templeton Center School200807200020Core ProgramDesign Development$47,563,18463.11 %$1,824,491$21,104,406$28,419,565